2027-31 Capital Improvement Plan
2032 Full-Depth Pavement Reconstruction Project Name 2032 Full-Depth Pavement Reconstruction Project # CIF-32-001
Total Project Cost $450,000
City Engineer Improvement 1 - Have to do
Contact
Capital Improvements Fund
Department
Type
Street Reconstruction
Category
Priority
Active
30 years
Status
Useful Life
Capital Improvement Fund
Fund
Description
This project is for the full depth reconstruction of the bituminous roadway for Vierling Drive between Polks St and Spencer St and Eastview Circle and Prairie St S. The project will include converting the roadway from 4 lanes to 3 lanes to address safety and speeding issues along the corridor.
Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.
Prior
Expenditures
2027
2028
2029
2030
2031
Total
0
Engineering/Administration
0
0
0
0
450,000
450,000
0
0
0
0
450,000
450,000
Total
Prior
Funding Sources
2027
2028
2029
2030
2031
Total
0
Capital Improvement Fund
0
0
0
0
450,000
450,000
0
0
0
0
450,000
450,000
Total
Budget Impact
The reconstruction of roadways is necessary to replace the complete pavement section after they have degraded beyond the point where maintenance such as overlays, potholes repair and patching is effective.
Produced Using Plan-It CIP Software
74
Made with FlippingBook flipbook maker