2027-31 Capital Improvement Plan

2032 Full-Depth Pavement Reconstruction Project Name 2032 Full-Depth Pavement Reconstruction Project # CIF-32-001

Total Project Cost $450,000

City Engineer Improvement 1 - Have to do

Contact

Capital Improvements Fund

Department

Type

Street Reconstruction

Category

Priority

Active

30 years

Status

Useful Life

Capital Improvement Fund

Fund

Description

This project is for the full depth reconstruction of the bituminous roadway for Vierling Drive between Polks St and Spencer St and Eastview Circle and Prairie St S. The project will include converting the roadway from 4 lanes to 3 lanes to address safety and speeding issues along the corridor.

Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.

Prior

Expenditures

2027

2028

2029

2030

2031

Total

0

Engineering/Administration

0

0

0

0

450,000

450,000

0

0

0

0

450,000

450,000

Total

Prior

Funding Sources

2027

2028

2029

2030

2031

Total

0

Capital Improvement Fund

0

0

0

0

450,000

450,000

0

0

0

0

450,000

450,000

Total

Budget Impact

The reconstruction of roadways is necessary to replace the complete pavement section after they have degraded beyond the point where maintenance such as overlays, potholes repair and patching is effective.