ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects

BULGARIA

TRA-N-140

Interconnection Turkey-Bulgaria

Non-FID

Pipeline including CS

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter Operator TEN-E Project ?

Bulgartransgaz EAD Bulgartransgaz EAD

Project of Common Interest Yes

Interested by PCI ? IGAs

2

Web Link

http://www.bulgartransgaz.bg/en/index.php

Bulgartransgaz EAD for the gas pipeline section on the territory of Bulgaria (100%)

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime

End of permitting phase

# of Pipelines, nodes, CS Total Pipeline Length (km)

Not applicable Not applicable

2 +205,00

FID Construction Commissioning Last completed Phase :

Total CS Power (MW) Expected Load Factor

Not relevant

Not relevant

2016

% Exemption in entry direction % Exemption in exit direction

0%

Planned

0%

| 11

GRIP Central Eastern Europe 2014–2023 Annex B

Made with