ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects
HUNGARY
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit Yes entry Yes exit Yes entry
Vecsés MGT / FGSZ
51,00 25,50 153,00
Hub Hungary Hub Hungary (SK-HU Hub Hungary
Hub Hungary Hub Austria Hub Hungary Hub Hungary (SK-HU Interconnector)
Mosonmagyarovar
25,00
Hub Austria
DESCRIPTION OF THE PROJECT
Pipeline between Városföld-Ercsi and 'LJƅƌ nodes, DN1000, PN100, 210 km.This project will enable the Mosonmagyarovar interconnection point to reach its full capacity of 153 GWh/d from Austria to Hungary.It will also enable the Mosonmagyarovar interconnection point to realize reverse flow capacity up to 153 GWh/d from Hungary to Austria as well.
EXPECTED BENEFITS
Security of Supply, Market integration (Increase AT/HU border capacity, Security of Supply of Western Hungary, new power plant supply, Reverse fllow HU>AT, Increase capacity Sk>HU and HU>SK, Create capacity RO>AT), Reverse Flows, Diversification of sources, o The Hungarian projects taken as a whole main aim, is to enhance the flexibility of the Hungarian transmission system by connecting to neighbouring systems, ensuring reserves flow availability, and guaranteeing flow deliverability which will enhance the transmission systems security of supply position along with helping with further market integration. ,
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing