ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects

HUNGARY

TRA-F-148

Slovak-Hungarian interconnector (Vecsés-Szada-Balassagyarmat)

FID

Pipeline including CS

SPONSORS

GENERAL INFORMATION

FINANCING

ƵƐƚƌĞĂŵ ;ϭϱйͿ

Promoter Operator TEN-E Project ?

Magyar Gaz Tranzit Zrt. MGT Hungarian Gas Transit Ltd.

Not part of TEN-E Not defined yet

Interested by PCI ? IGAs

1

Web Link

D'd ƌƚ͘ ;ϴϱйͿ

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime

End of permitting phase

# of Pipelines, nodes, CS Total Pipeline Length (km)

regulated regulated

2014

2

FID Construction Commissioning Last completed Phase :

+110,00

Total CS Power (MW) Expected Load Factor

No

2013 2014/1

no

% Exemption in entry direction % Exemption in exit direction

0%

Construction

0%

| 122

GRIP Central Eastern Europe 2014–2023 Annex B