ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects

BULGARIA

TRA-N-149

Interconnector Greece Bulgaria - IGB

Non-FID

Pipeline including CS

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter Operator TEN-E Project ?

DEPA S.A. ICGB a.d.

Not part of TEN-E Yes

Interested by PCI ? IGAs

None

IGI Poseidon S.A. (50%)

Bulgarian Energy Holding EAD (50%)

Web Link

www.icgb.eu

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime

End of permitting phase

# of Pipelines, nodes, CS Total Pipeline Length (km)

Negotiated (e.g. Exemption) Negotiated (e.g. Exemption)

2014 Q1

2

FID Construction Commissioning Last completed Phase :

2014 Q2

+182,00

Total CS Power (MW) Expected Load Factor

Yes

2014 Q3 2016/1

+10,00

Not yet

% Exemption in entry direction % Exemption in exit direction

0%

Permitting

0%

| 18

GRIP Central Eastern Europe 2014–2023 Annex B