ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects

BULGARIA

TRA-N-308

South Stream Bulgaria - Stage I

Non-FID

Pipeline including CS

SPONSORS

GENERAL INFORMATION

FINANCING

South Stream Bulgaria AD (Bulgarian Bulgartransgaz EAD

Promoter Operator TEN-E Project ?

Not part of TEN-E Not defined yet

Interested by PCI ? IGAs

None

Web Link

Bulgartransgaz EAD (100%)

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime

End of permitting phase

# of Pipelines, nodes, CS Total Pipeline Length (km)

Not applicable Not applicable

FID Construction Commissioning Last completed Phase :

Total CS Power (MW) Expected Load Factor

Not relevant

Not relevant

2015

% Exemption in entry direction % Exemption in exit direction

0%

0%

| 24

GRIP Central Eastern Europe 2014–2023 Annex B

Made with