ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects

CROATIA

TRA-N-068

Ionian Adriatic Pipeline

Non-FID

Pipeline including CS

SPONSORS

GENERAL INFORMATION

FINANCING

Croatia (From Split to Montenegro border), Plinacro Ltd; Ministry of Economy (Croatia) (100%)

Fieri to Montenegro border, Ministry of Economy , Trade and Energy (Albania) (100%)

Promoter Operator TEN-E Project ?

Plinacro Ltd Plinacro Ltd

Not part of TEN-E Yes

Interested by PCI ? IGAs

2

Web Link

www.plinacro.hr

Bosnia and Herzegovina, BH Gas (Bosnia and Herzegovina); Ministry of Foreign Trade and Economic Relations (BiH) (100%)

Montenegro, Ministry of Economy (Montenegro) (100%)

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime

End of permitting phase

# of Pipelines, nodes, CS Total Pipeline Length (km)

Regulated Regulated

3 +540,00

FID Construction Commissioning Last completed Phase :

Total CS Power (MW) Expected Load Factor

No

2015 2020

No

% Exemption in entry direction % Exemption in exit direction

0%

Planned

0%

| 31

GRIP Central Eastern Europe 2014–2023 Annex B