ENTSOG GRIP CEE 2014-2023 / Annex B : Infrastructure Projects

GERMANY

Expansion of Nord Stream connection to markets in western Europe - Entry Greifswalder Bodden area

TRA-N-323

Non-FID

Pipeline including CS

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter Operator TEN-E Project ?

GASCADE Gastransport GmbH NEL Gastransport GmbH

Not part of TEN-E No

Interested by PCI ? IGAs

None

Web Link

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Applied for Exemption ? Exemption granted ? Considered TPA Regime Considered Tariff Regime

End of permitting phase

# of Pipelines, nodes, CS Total Pipeline Length (km)

Regulated Regulated

1

FID Construction Commissioning Last completed Phase :

Total CS Power (MW) Expected Load Factor

Not relevant

+171,00

Not relevant

2022

% Exemption in entry direction % Exemption in exit direction

0%

Planned

0%

| 61

GRIP Central Eastern Europe 2014–2023 Annex B

Made with