ENTSOG GRIP CEE 2014-2023 / Main Report
PROJECT PROMOTER
PROJECT NAME
CODE
COMMISSIONING
Number of investment projects in CEE GRIP 2014–2023
Bulgartransgaz EAD
TRA-N-140
2016
Interconnection Turkey-Bulgaria (ITB)
TRA-N-298
2017
Rehabilitation, Modernization and Expansion of the National Transmission System
eustream, a.s.
TRA-F-016
2015
Slovakia - Hungary interconnection
TRA-F-017
2017
System Enhancements – Eustream
TRA-N-190
2019
Poland - Slovakia interconnection
Gasunie Deutschland Transport Services GmbH
TRA-F-231
2014
Extension of existing gas transmission capacity in the direction to Denmark – 1. Step
TRA-N-232
2015/2016
Extension of existing gas transmission capacity in the direction to Denmark – 2. Step
TRA-N-316
2020
Expansion of Nord Stream connection to markets in western Europe – Exit Bunde - Oude
Gasunie Ostsee- anbindungsleitung GmbH
TRA-N-321
2020
Expansion of Nord Stream connection to markets in western Europe – Entry Greifswald
Gas Connect Austria GmbH
TRA-N-021
2019
Bidirectional Austrian-Czech Interconnector (BACI)
GASCADE Gastransport GmbH
TRA-F-292
2014
Installing a reverse flow in Mallnow
TRA-F-289
2014
Installation of Nord Stream onshore project
TRA-N-249
2014
Extension of GASCADE grid in the context of the Nord Stream (on-shore) project
TRA-N-291
2018
New net connection from Rehden to Drohne (new covenant from NEP2012)
TRA-N-324
2022
Expansion of Nord Stream connection to markets in western Europe – Exit Eynatten
TRA-N-323
2022
Expansion of Nord Stream connection to markets in western Europe – Entry Greifswalder Bodden area
GAZ-SYSTEM S.A.
TRA-F-326
2013
Physical reverse flow on the metering station in Mallnow
TRA-F-248
2014
Upgrade of gas infrastructure in northern and central Poland
TRA-N-276
2015
Upgrade of the entry points in Lwówek and Włocławek on the Yamal-Europe pipeline
TRA-N-212
2018
Gas Interconnection Poland-Lithuania (GIPL)
TRA-N-247
2018
The North-South corridor in Western Poland
TRA-N-273
2019
PL - CZ interconnection
TRA-N-275
2019
PL - SK interconnection
TRA-N-271
2020
PL - DK interconnection (Baltic Pipe)
TRA-N-274
2021
Upgrade of PL-DE interconnection in Lasów
TRA-N-245
2023
The North-South Gas Corridor in Eastern Poland
GRTgaz Deutschland
TRA-F-327
2013
Gernsheim-MIDAL
FGSZ Ltd.
TRA-N-124
2015
Local Odorisation – FGSZ
TRA-N-286
2016
Romanian-Hungarian reverse flow Hungarian section
TRA-N-325
2017
Slovenian-Hungarian interconnector
TRA-N-019
2018
Csepel connecting pipeline
TRA-N-065
2021
Hajduszoboszlo CS
TRA-N-123
2023
Városföld CS
TRA-N-018
2023
Városföld - Ercsi - Győr
TRA-N-061
2023
Ercsi-Szazhalombatta
ICGB EAD
TRA-N-149
2016
Interconnection Greece - Bulgaria