Projects and Markets
Prior Experience/Projects
• Topsides modules of up to 4,500 tonnes, including
both process and accommodation modules for
engineering, procurement and construction
(EPC) projects
• Jackets of up to 9,000 tonnes, excluding piles
• Subsea manifolds
• Over 40 jackets for offshore wind EPC projects
• Wave and tidal generation projects
BiFab was very proud to be selected to fabricate the
substructure assemblies and associated components
required for the Beatrice Wind Farm Demonstrator
Project involving Talisman Energy (UK) Ltd and
Scottish and Southern Energy (SSE). Based on our
experience from previous projects, this was an
extremely fast track and challenging project and was
successful due to the good relationships, team effort
and excellent working environment created by the
management team of Talisman and SSE. This was the
first time two jacket structures on this scale had been
completely fabricated in a workshop environment.
The delivery schedule would have been significantly
more difficult if weather factors had to be considered.
Following the Beatrice project, we have now
completed projects for the supply of a further 41
jacket substructures for offshore wind.
31 for Ormonde Field Development UK – Vattenfall
6 for Alpha Ventus German Offshore Project – DOTI
2 for Greater Gabbard – Fluor/SSE/RWE
2 for Gwynt Y Mor – RWE Npower
>