CITY OF RALEIGH
PUBLIC UTILITIES
Monthly Performance Report
FY 15 (July 2014-June 2015)
26
All financial data is from the city’s financial management system. This is an unaudited report.
Project Name
Project
Manager
Current
Phase
Vendor
%
Completion
Date
Status
Walnut Creek LS Improvements
4th VTSH Pump
EN
Construction Dellinger
95%
9/2014
Construction Ongoing
Aversboro PS
EN
Construction
-
0%
-
Receive Bidgs August 2014
Walnut Creek LS Improvements
Screw Rehab
EN
On Hold
Hazen and
Sawyer
100%
-
Waiting Funding
Pump Station Rehab and Replacement
Hwy 50
RR
Construction
Water &
Waste
10%
12/2014
N-T-P June 2014
East Neuse Regional Pump Station
AB
PER/EIS
Jacobs
65%
8/2015
Received Draft EIS
Crabtree LS Improvements
EN
Pre-Design
TBD
0%
TBD
PS Evaluation Complete
Neuse River Pump Station Pump
Addition
RR
PER
Highfill
60%
9/2014
Evaluating Pump Options
PS Rehab and Replacement
Greenspring/Green Willow
RR
PER
Brown and
Caldwell
100%
2/2014
Scoping for Design Phase
Forestville Farms/Brighton/Wake High
Meadows PS Evaluation
RR
PER
Highfill
100%
9/2014
Complete
SEWER PUMP STATION PROJECTS
Project Name
Project
Manager
Current
Phase
Vendor
%
Completion
Date
Status
Expansion
Segment #4
EN
Construction
JF Wilkerson
Contracting
95%
9/2014
RR Encroachment Back to RR
Master Plan Update
EN
PER
CDM Smith 50%
12/2014
Neuse River Sampling Complete
Sunnybrook Reuse Tank Discharge
JG
PER
Kimley Horn
-
-
Scoping
REUSE WATER IMPROVEMENTS