Expected Gas Sourcing
Caspian Region, Russia
Time Schedule
Grant Obtention Date
Delay Since Last TYNDP
1 year
Delay Explanation
Russian/Turkey conflict.
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Hungarian section
+30 MW compressor station, in order to put natural gas from
the Hungarian national system (gas storage, other sources) to
Tesla pipeline.
1,200
361
50
Total
361
50
Schedule
Start Date
End Date
Pre-Feasibility
12/2015
Feasibility
01/2017
12/2017
FEED
10/2016
03/2018
Market Test
10/2016
Permitting
10/2016
03/2018
Supply Contracts
08/2018
FID
03/2018
Construction
09/2018
05/2020
Commissioning
2020
2020
NDP and PCI Information
Part of NDP
Yes (Hungarian TYNDP 2015)
NDP Number
12.15.1. - 12.15.2.
Currently PCI
Yes (6.25.2.)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 332 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
154