LARINO - RECANATI Adriatic coast backbone
General Information
Promoter
Società Gasdotti Italia
Operator
Società Gasdotti Italia
Host Country
Italy
Status
Planned
Website
Publication Approval Status
Approved
Sponsors
TRA-N-974
Project
Pipeline including CS
Non-FID
Update Date
25/05/2016
Advanced
Description
Complete the realisation of a Gas Tranportation system on Adriatic coast. The project forsees the development under 5 phases of the main backbone
and the compression station. Of these 5 phases, one section is already completed and another one is under construction. - 1 Construction of 110 km
24" LARINO-CHIETI - 55 km 20" CHIETI - CELLINO (already completed and running) - 90 km 20" CELLINO - SAN MARCO (15 km completed and 75
km under construction) - Construction of 32 km 24" SAN MARCO Recanati - Construction 3 MW compression station SAN MARCO
Regulatory Decisions and
similar material conditions
The construction and operation of each project section has been already authorized by MISE (Italian Ministry of Economic Development) as part of
the National Gas Network. Decree No. 14624 of 25 May 2016, the Italian Ministry of Economic Development has assessed the consistency of SGI's
TYNDP with the National Energy Strategy. SGI has included the project in its own TYNDP, as submitted to MiSE and the NRS (AEEGSI). TYNDP
approval process is currently being revised due to the transfer of the relevant competences from MiSE to AEEGSI.
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Larino (IT)
Società Gasdotti Italia
2022
IT
ITg
53.0 GWh/d
Comment: Capacity values refer to the whole completed project
Società Gasdotti Italia
2022
ITg
IT
53.0 GWh/d
Comment: Capacity values refer to the whole completed project
Recanati (IT)
Società Gasdotti Italia
2022
IT
ITg
53.0 GWh/d
Comment: Capacity values refer to the whole completed project
Società Gasdotti Italia
2022
ITg
IT
53.0 GWh/d
Comment: Capacity values refer to the whole completed project
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 381 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
218