Expected Gas Sourcing
Caspian Region, LNG (), Black Sea
Time Schedule
Grant Obtention Date
18/05/2015
Delay Since Last TYNDP
Stage 1- 9 months delay in commissioning Stage 2 – 21 months in commissioning
Delay Explanation
Stage 1 – delay in the tender for teh FEED services related to the compresor stations Stage 2 – uncertainties related to the execution of the
infrastructure which enables the connection with the production at the Black Sea
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Podisor - Horia
813
528
50
Total
528
50
Schedule
Start Date
End Date
Pre-Feasibility
12/2013
Feasibility
01/2014
12/2014
FEED
01/2016
02/2017
Market Test
10/2017
Permitting
01/2014
02/2017
Supply Contracts
FID
Construction
08/2017
09/2020
Commissioning
2020
2020
NDP and PCI Information
Part of NDP
Yes (Development Plan for the National
GTS 2016-2025)
NDP Number
7.1
Currently PCI
Yes (Stage I: 6.24.2 Stage II: 6.24.7)
CBCA Decision
Yes (2015-10-06)
Market Survey
Open Season(2017-10-02)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 481 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
237