Expected Gas Sourcing
Caspian Region, Norway, Russia, LNG (TR), Iraq, Iran, Egypt, Israel, Turkmenistan, Kazakhstan, Cyprus, Azerbaijan, Any gas available at Turkish/European HUBs. For dire
Benefits
Main Driver
Regulation SoS
Main Driver Explanation
The project brings benefits to the SoS, bringing the new sources of gas supply and South-Eastern Europe countries, towards the Central and Western
Europe markets, while further enhancing the market integration of the affected countries.
Benefit Description
- Physical alternative for providing gas from other sources, for all Balkan countries' consumption; - Providing security of supply for the Balkan countries'
consumption; - Additional utilization for transit and storage assets; - Providing Western shippers with possibility to supply to Balkan countries and even
Turkey from different other gas surces located in Europe; - Corridor ready for future gas imports to Europe from the Southern Corridor and other
alternative sources.
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2021
2025
NDP and PCI Information
Part of NDP
No (For the moment, the project lacks
sufficient descriptive elements in order for
it to be included in the National Gas
Transmission System Development Plan.)
NDP Number
Currently PCI
Yes (6.25.1)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 496 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
243