Further enlargement of the BG—RO—HU—AT transmission corridor (BRUA) phase 3
General Information
Promoter
SNTGN Transgaz SA
Operator
SNTGN Transgaz S.A.
Host Country
Romania
Status
Planned
Website
Publication Approval Status
Approved
Sponsors
SNTGN Transgaz SA
100%
TRA-N-959
Project
Pipeline including CS
Non-FID
Update Date
22/06/2016
Non-Advanced
Description
Development of gas transmission capacity on the Oneşti – Coroi – Haţeg – Nădlac corridor depending on the available gas quantities at the Black
Sea shore or from other on-shore blocks. The development of this gas transmission corridor requires: � the rehabilitation of some of the NTS
existing pipelines; � replacement of some of the NTS existing pipelines with new pipelines or the building of new pipelines installed in parallel with
the existing ones; � development of 4 or 5 new compressor stations having a total installed power of approximately 66- 82.5MW.
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Csanadpalota 2
SNTGN Transgaz S.A.
2023
HU
RO
128.7 GWh/d
SNTGN Transgaz S.A.
2023
RO
HU
128.7 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM