M3 pipeline reconstruction from CS Ajdovščina to Šempeter/Gorizia

General Information

Promoter

Plinovodi d.o.o.

Operator

Plinovodi d.o.o.

Host Country

Slovenia

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

Plinovodi

100%

TRA-N-108

Project

Pipeline including CS

Non-FID

Update Date

22/05/2016

Non-Advanced

Description

Interconnector with the Italian TSO. Adjustment to operating parameters of the transmission system of the Italian TSO.

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Gorizia (IT) /Šempeter (SI)

Plinovodi d.o.o.

2020

IT

SI

35.5 GWh/d

Plinovodi d.o.o.

2020

SI

IT

38.0 GWh/d