Physics Bucharest 2017

Estimated Time for Commissioning

• It takes 30 hours for • One PDD and five depth profiles for 15 field sizes for each of five beam modifiers (one open and four physical wedges) for a dual energy accelerator • 1.5 week for photon beam scanning • Equipment setup, change in machine parameters, machine faults, …

• 1 week for point dose collection • 1-2 weeks for electron beams • 1-2 weeks analysis and report writing

4-6 weeks for commissioning (excluding acceptance)