Road to Rio - Performance Planning Document
Performance Planning Process and Timeline
Key Dates • 23 Oct
Communication to all High Performance NGBs regarding the performance planning process for Rio.
24 Oct – 23 Nov
Systems profile of NGB HP programme for Rio cycle and submission to ISC.
•
23 Nov
Deadline for submitting systems profile.
•
24 Oct – 21 Dec
NGBs construct Rio High Performance Strategic Plan (Rio Strategy). Consultation with IIS and ISC. Deadline for submitting Rio Strategy, 2013 HP Plan and Investment Plans to the ISC.
•
21 Dec
•
21 Dec – 20 Jan ‘13
Technical and financial analysis of plans. Feedback provided.
•
21 Jan – 08 Feb 08 Feb – 22 Feb
NGB presentations of Rio Strategy.
•
Final analysis and investment proposals prepared for decision. Investment proposal presented to High Performance Committee.
•
22 Feb 05 Mar
•
Investment proposal presented to ISC Board.
•
High Performance Plan and Investment Application Process Timeline for 2013 Plans
22/2 Investment Proposal Presented to HPC
23/11 Systems Profile Submissions Deadline (4pm)
5/3 Investment Proposal Presented to ISC Board
21/12 Plans Submissions Deadline (4pm)
23/10 Communication to NGBs
21/1 - 8/2 NGB Presentations
8/2 - 22/2 Investment Proposals Prepared
17/9 - 5/11 Debrief Process for NGBs
5/11 - 21/12 Rio Strategic Plan, 2013 HP Plan and Investment Plans Consultation/Construction Phase
21/12 - 20/1 Technical & Financial Analysis. Feedback Provided
Oct-12
Nov-12
Dec-12
Jan-13
Feb-13
Mar-13
23/10 - 22/11 Systems Profiling Phase