ENTSOG GRIP South - ANNEX A: Infrastructure Projects

TRA-N-043

Val de Saône project

Non-FID

Pipeline includingCS

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter Operator TEN-EProject ?

GRTgaz GRTgaz

Notpartof TEN-E Yes

InterestedbyPCI ? IGAs

None

http://www.grtgaz.com/fileadmin/plaquettes/en/10year s2013_2022_EN.pdf

WebLink

Private Financing (100,00%)

Core system developments, GRTgaz (100%)

THIRD-PARTYACCESSREGIME

SCHEDULE

TECHNICAL INFORMATION

#of Pipelines, nodes, CS Total Pipeline Length (km) Total CompressorPower (MW) Expected LoadFactor

Applied for Exemption? Exemptiongranted? ConsideredTPARegime ConsideredTariffRegime

Endof permittingphase

1 +190,00

Regulated Regulated

FID Construction Commissioning Last completedPhase :

Not relevant

+9,00

Not relevant

2018

%Exemption inentrydirection %Exemption inexitdirection

0%

Planned

0%

| 20

ENTSOG–GRIPSouth 2013–2022AnnexA

Made with