The permit must always be signed by the departmen- tal manager, steward, person responsible for zone or shutdown manager. The client-project leader must indicate the name, location and telephone number of the persons involved. The works may only be started if ALL safety measures have been implemented and checked on site and after the permit has been signed for release. If an unforeseen situation is determined, the works should stop in order to first assess or reassess the risks. On ending the works, the departmental manager, steward, person responsible for zone or shutdown manager should always be informed.