Decommissioning Insight 2016 - Oil & Gas UK
Northern North Sea and West of Shetland • The number of wells forecast for P&A over the next ten years in the northern North Sea and west of Shetland has increased to 430 from 326 in the 2015 survey. • The addition of 81 platform wells and 23 subsea wells is due to two large platform removal projects and a subsea project that now expect to carry out decommissioning earlier due to the challenges of operating in a low oil price environment.
1
2
3
• Seventy-three per cent of wells for P&A in these regions are platform wells.
• Forty-eight wells are forecast to be plugged and abandoned in 2016, with an annual average of 65 wells between 2016 and 2018.
4
• As several P&A campaigns are likely to start earlier to take advantage of current low rig rates, 80 more wells are expected in the near term (2016 to 2018).
• Activity is forecast to spike at 79 wells in 2023 due to the three new projects in the northern North Sea.
5
Figure 4: Number of Wells Forecast to be Plugged and Abandoned in the Northern North Sea and West of Shetland
6
140
Platform Subsea Development Suspended Subsea E&A Wells
Increased Uncertainty in Forecasts
120
7
100
80
8
60
9
Number of Wells
40
20
0
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Source: Oil & Gas UK
Number of Wells 2016 to 2025 Proportion that are Platform Wells
Total CNS
1,074
52% 37% 73%
644 430
NNS and W o S
15