FY 2020-2024 Capital Improvement Plan

Capital Improvement Plan City of Spencer, Iowa

thru FY 20 FY 24

Contact Public Works Director Department Safe Routes to School

Type Improvement

23-SRTS-001

Project #

Useful Life 30 Years

Project Name 5th AVE E SIDEWALK

Priority 3 - Important Category Sidewalks

Description The proposed project will complete the sidewalk system on 5th Avenue East from East 16th Street to East 19th Street. The project will also include ADA compliant ramps Total Project Cost: $75,000

Justification The project will complete the sidewalk system that connects to Fairview School.

Expenditures Planning/Design

Total

FY 20

FY 21

FY 22

FY 23

FY 24

7,500

7,500

67,500 75,000

67,500 75,000

Construction/Maintenance

Total

Funding Sources

Total

FY 20

FY 21

FY 22

FY 23

FY 24

75,000 75,000

75,000 75,000

SRTS Reserve

Total

Made with FlippingBook - Online catalogs