2020-24 Capital Improvement Plan
Capital Improvement Plan City of Shakopee, Minnesota PA-19-09 Project Name Memorial Park Bridge Project #
thru 2020 2024
Department Park Asset Internal Serv. Fund
Contact Public Works Director
Type Memorial Park
Useful Life 50
Category Bridges
Priority 1 Critical for Safety/Preservati
Accounting Code 5835/6835
Status Active
Fund Park Asset IS Fund
Description Replacement of bridge that was removed connecting Memorial Park to the MN Valley State Trail over backwater channel of the MN River. Approximately 830-ft of 10-ft wide trail will be constructed, connecting to the State Trail on the north side of the channel and southerly through Memorial Park to the State Trail along CH 101. Total Project Cost: $800,000
Justification Bridge will be utilized by pedestrians, cyclists, snowmobiles and connect to the MN Valley State Trail
Prior
Expenditures Improvements
2020
2021
2022
2023
2024
Total
100,000
590,000 110,000 700,000
590,000 110,000 700,000
Engineering/Administration
Total
Total
Prior
Funding Sources Contributions/Donations Cost Sharing, County
Total
2020
2021
2022
2023
2024
100,000
100,000 50,000 300,000 250,000
100,000 50,000 300,000 250,000
Total
Grants
Park Asset Internal Service Fund
700,000
700,000
Total
Budget Impact/Other Yearly inspection will be required
130