2020-24 Capital Improvement Plan
Capital Improvement Plan City of Shakopee, Minnesota
thru 2020 2024
Contact Parks & Recreation Director Department Building Internal Service Fun
Type Buildings
BA-20-007
Project #
Useful Life
Project Name Community Center Fitness Center Floor Repair
Category Recreation
Priority 1 Critical for Safety/Preservati
Accounting Code
Status Active
Fund Building Asset IS Fund
Description Repair of uneven surface and underlying support structure in community center fitness area.
Total Project Cost: $50,000
Justification There are cracks forming in the Community Center fitness area due to certain construction flaws. There is no significant structural risk according to a study performed by a consultant. However, the cracks will continue to grow and could pose trip and fall risks, as well as cause aesthetic issues. If left unresolved, the cracks will grow larger.
Expenditures
2020
2021
2022
2023
2024
Total
50,000 50,000
50,000 50,000
Construction/Maintenance
Total
Funding Sources
Total
2020
2021
2022
2023
2024
50,000 50,000
50,000 50,000
Building Internal Service Fund
Total
Budget Impact/Other
175