2020-24 Capital Improvement Plan

Capital Improvement Plan City of Shakopee, Minnesota

thru 2020 2024

Department Park Development Fund

Contact Director of Planning & Develo

Type Improvement

PR-22-002

Project #

Useful Life 30

Project Name Southbridge Regional Trail Connection (Savannah)

Category Trails

Priority 2 Important-Provide Efficienci

Accounting Code

Status Active

Fund Park Development Fund

Description The Parks System Master Plan provides guidance to complete a missing gap in the regional trail network through the Southbridge neighborhood from TH 169 to Southbridge Parkway. The exact route needs to be identified and vetted with the community. Justification Trail connections provides off street transportation through Southbridge neighborhoods and enhances Savannah Oaks Park where a trail stub is currently constructed. This trail search corridor is part of the RBTN Tier 2 network. This missing segment will also be instrumental with the of a TH 169 trail bridge crossing. Total Project Cost: $190,000

Expenditures Planning/Design Improvements

2020

2021

2022

2023

2024

Total

30,000

30,000 160,000 190,000

160,000 160,000

30,000

Total

Funding Sources

Total

2020

2021

2022

2023

2024

30,000 30,000

160,000 160,000

190,000 190,000

Cost Sharing

Total

Budget Impact/Other Annual maintenance estimated at $2,500

24

Made with FlippingBook flipbook maker