2026-2030 Capital Improvement Plan
Community Center Weight Equipment Replacement 2026 thru 2030 Project Details Shakopee, MN Project # Project Name Total Project Cost
BA-26-010
Community Center Weight Equipment Replacement
$130,800
Contact
Parks & Recreation Director
Department
Building Internal Service Fund
Type
Equipment
Category
Recreation
Priority
2 - Smart to do
Status
Active
Useful Life
10 years
Description Replace all free weight and selectorized strength training equipment at the Shakopee Community Center.
Justification The existing free weight and selectorized strength equipment at the Shakopee Community Center is nearing or has exceeded its estimated useful life. As equipment ages, it becomes more costly to maintain, less reliable, and less appealing to users. Upgrading to modern, high-quality equipment will enhance the member experience, improve safety, and align with current fitness trends and user expectations. Investing in new equipment also serves as a strategic driver for both new membership acquisition and member retention, ultimately increasing revenue and supporting the long-term sustainability of the facility.
Expenditures
2026
2027
2028
2029
2030
Total
130,800 130,800
Equip/Vehicles/Furnishings
130,800 130,800
0 0
0 0
0 0
0 0
Total
Funding Sources
2026
2027
2028
2029
2030
Total
130,800 130,800
Building Internal Service Fund
130,800 130,800
0 0
0 0
0 0
0 0
Total
180
Produced Using Plan-It CIP Software