2026-2030 Capital Improvement Plan
2026 Full Depth Pavement Reconstruction 2026 thru 2030 Project Details Shakopee, MN Project # Project Name
CIF-26-001
2026 Full-Depth Pavement Reconstruction
Total Project Cost
$2,885,000
Contact
City Engineer Improvement 1 - Have to do
Department
Capital Improvements Fund
Type
Category
Street Reconstruction
Priority
Status
Active
Useful Life
25 years
Fund
Capital Improvement Fund
Description This project is for the full depth reconstruction of the bituminous roadway for Crossings Boulevard from Country Road 18 to approximately 710 feet west of Foothill Trail and 12th Avenue from east of County Road 83 to Valley Park Drive. With this project, 12th Avenue will be converted from a 4-lane to a 3-lane section as recommended by a transportation study that was completed in 2019. Additionally, the intersection of 12th Avenue and Valley Park Drive will be evaluated for proper traffic control and configuration. Utility, curb and gutter repairs and improvements will be evaluated and included with this project.
Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.
Prior
Expenditures
2026 2027 2028 2029 2030
Total
2,580,000
140,000
Construction/Maintenance Engineering/Administration
2,580,000
0 0 0
0 0 0
0 0 0
0 0 0
165,000
165,000
Total
2,745,000
2,745,000
Prior
Funding Sources
2026 2027 2028 2029 2030
Total
2,100,000
140,000
Capital Improvement Fund
2,100,000
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
530,000 55,000 45,000 15,000
Special Assessments Sanitary Sewer Fund Cost Sharing, SPUC Storm Drainage Fund
530,000 55,000 45,000 15,000
Total
2,745,000
2,745,000
Budget Impact Required ADA improvements are generally unfunded mandates to improve accessibility and to minimize liability.