2026-2030 Capital Improvement Plan
Annual Trail Rehabilitation (along roadways) 2026 thru 2030 Project Details Shakopee, MN Project # Project Name
CIF-26-003
Annual Trail Rehabilitation (along roadways)
Total Project Cost
$1,414,000
Contact
City Engineer Improvement 1 - Have to do
Department
Capital Improvements Fund
Type
Category
Trails Active
Priority
Status
Useful Life
10 years
Fund
Capital Improvement Fund
Description This project includes the reconstruction of existing bituminous trails in the city, along city or county roadways. The 2026 project includes the trail connecting Polk St S and along Crossings Boulevard from Ridge Creek Park to CR 18.
Justification The age and condition of the bituminous trail segments require rehabilitation. The City must reconstruct pedestrian ramp facilities to comply with its ADA Transition plan adopted in 2018, increasing the cost of future overlay projects compared to previous years' projects.
Prior
Expenditures
2026
2027
2028
2029
2030
Total
1,031,500
240,000
Construction/Maintenance Engineering/Administration
110,000
176,000
312,000
213,500
220,000
142,500
15,000
24,000
43,000
30,500
30,000
Total
125,000
200,000
355,000
244,000
250,000
1,174,000
Prior
Funding Sources
2026
2027
2028
2029
2030
Total
1,174,000 1,174,000
240,000
Capital Improvement Fund
125,000 125,000
200,000 200,000
355,000 355,000
244,000 244,000
250,000 250,000
Total
Budget Impact Required ADA improvements are generally unfunded mandates to improve accessibility and to minimize liability.