2026-2030 Capital Improvement Plan

Annual Pavement Rehabilitation 2026 thru 2030 Project Details Shakopee, MN Project #

CIF-26-006

Project Name

Annual Pavement Rehabilitation

Total Project Cost

$1,675,000

Contact

City Engineer Improvement 1 - Have to do

Department

Capital Improvements Fund

Type

Category

Street Paving

Priority

Status

Active

Useful Life

7 years

Fund

Capital Improvement Fund

Description The 2026 project is for the rehabilitation of the bituminous roadways for citywide.The rehabilitation work includes crack sealing and repair, minor concrete repairs, partial and full depth spot patching and pavement repair, utility repairs and a chip seal coat of the bituminous surface. The project also includes a seal coat and restriping of Eagle Creek Boulevard between CH17 and CH83 as a 3-lane roadway section.

Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.

Prior

Expenditures

2026

2027

2028

2029

2030

Total

1,228,500

240,000

Construction/Maintenance Engineering/Administration

300,000

221,000

229,500

238,000

240,000

206,500

40,000

39,000

40,500

42,000

45,000

Total

340,000

260,000

270,000

280,000

285,000

1,435,000

Prior

Funding Sources

2026

2027

2028

2029

2030

Total

1,435,000 1,435,000

240,000

Capital Improvement Fund

340,000 340,000

260,000 260,000

270,000 270,000

280,000 280,000

285,000 285,000

Total

Budget Impact The rehabilitation of the pavements in the project area are necessary to preserve the existing pavement surface and delay the need for a bituminous overlayment or reclamation.