The Raubex Construction and Roadmac Surfacing team.

Cold winter season Although many of the complexities encoun- tered could be attributed to the cold winter season when asphalt batching started, one of the biggest challenges was the excessive fines generated at the plant. It was possible through close collaboration between the contractor and the supplier to solve this, and the company is now able to meet the very onerous RA requirements on other road construction contracts moving forward. Also playing an invaluable role in keeping works on track was the specific focus areas of each participant in the consortium. Raubex deployed its own team whose responsibilities ended with the priming of layers, after which Roadmac Surfacing commences operations that end with the

One of the successes of this project is the focus areas of each member of the consortium, with Roadmac Surfacing placing all of its attention on the asphalt.