AOAC SPADA February 2015 Meeting Book
Timeline of current project
February 3 – 4, 2015 - Project Launch – SPADA and WG meetings February – April 2015 - WG teleconferences to develop Draft SMPRs April 2015 - Face-to-face WG meetings, one for each agent, to discuss/revise Draft SMPRs May – June 2015 WG t l f t ti t d ft SMPR - e econ erences o con nue o ra s June 2015 - AOAC outreach and post SMPRs on AOAC website for public comment
11
Timeline of current project July – August 2015 - Preparation for final draft SMPR for each agent by WG Chair and
AOAC Chief Scientific Officer Collect and compile comments Address comments Revise SMPRs as appropriate
August – September 2015 - WG Teleconferences Resolve issues A gree on na ra
fi l d ft SMPR t b b itt d f SPADA o e su m e or
l approva
September 2015 - SPADA face-to face meeting to discuss/approve SMPRs
12
Made with FlippingBook