Timeline of current project

 February 3 – 4, 2015 - Project Launch – SPADA and WG meetings  February – April 2015 - WG teleconferences to develop Draft SMPRs  April 2015 - Face-to-face WG meetings, one for each agent, to discuss/revise Draft SMPRs  May – June 2015 WG t l f t ti t d ft SMPR - e econ erences o con nue o ra s  June 2015 - AOAC outreach and post SMPRs on AOAC website for public comment

11

Timeline of current project  July – August 2015 - Preparation for final draft SMPR for each agent by WG Chair and

AOAC Chief Scientific Officer  Collect and compile comments  Address comments  Revise SMPRs as appropriate

 August – September 2015 - WG Teleconferences  Resolve issues A  gree on na ra

fi l d ft SMPR t b b itt d f SPADA o e su m e or

l approva

 September 2015 - SPADA face-to face meeting to discuss/approve SMPRs