ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Main Report
NO.
PROJECT
CODE
STATUS
TSO / SPONSOR
TSO PROJECTS 1
Interconnection Croatia / Bosnia and Herzegovina (Slobodnica– Bosanski Brod–Zenica)
TRA-N-066 non-FID
2
Interconnection Croatia / Serbia Slobdnica – Sotin (Croatia) – Bačko Novo Selo (Serbia)
TRA-N-070 non-FID
Interconnection Croatia / Slovenia (Bosiljevo – Karlovac – Lučko – Zabok – Rogatec)
TRA-N-086 non-FID PCI 6.6.
3
4
Interconnection Croatia–Bosnia and Herzegovina (Licka Jesenica – Rakovica – Trzac – Bosanska Krupa with branches to Bihać and Velika Kladuša)
TRA-N-303 non-FID
5
Interconnection Croatia–Bosnia and Herzegovina (South)
TRA-N-302 non-FID
6
International Pipeline Omišalj – Casal Borsetti
TRA-N-083 non-FID
7
Ionian Adriatic Pipeline
TRA-N-068
non-FID PCI 6.21.
LNG evacuation pipeline Omišalj – Zlobin – Rupa (Croatia) / Jelšane (Slovenia)
TRA-N-090 non-FID PCI 6.5.3.
8
9
LNG main gas transit pipeline (Part of North-South Gas Corridor) Zlobin – Bosiljevo – Sisak – Kozarac – Slobodnica
TRA-N-075 non-FID PCI 6.5.2.
LNG-N-082 non-FID PCI 6.5.1.
10* LNG Regasification Vessel
* On 28 May 2014, sponsorship of this project was transferred to LNG Hrvatska Ltd, a subsidiary of Plinacro and the Croatian Electricity Company (HEP)
Image courtesy of Plinacro
Southern Corridor GRIP 2014–2023 |
17
Made with FlippingBook