Civil Engineering Contractors

Winner

Majuba Rail – Vaal Incremental Launch Bridge

18

The incremental launch bridge is one of the most highly mechanised erection methods used in bridge construction. The construction methodology follows the manufacturing of the superstructure of the bridge in a prefabrication area behind one of the abutments. Each new segment is concreted directly against the preceding one and after it has reached required design strength, it is moved forward by the length of one segment. One of the many challenges faced during construction of the piers was the diversion of the river in stages to gain access for the pier and abutment bases. A further issue is that the construction programme called for the piers to be cast during the rainy season (September 2013 - January 2014), making constructability almost impossible. The nine piers (average height 1,89 m) were cast using a climbing shutter. With the incremental launch method, the advantages of the in situ and precast construction methods are combined for maximum benefit. The prefabrication area includes the tower crane, the steel fixing area – as well as storage area for the rebar, the launching yard formwork area and the pre stressing

The employer’s objective is to construct an electrified heavy haul rail line linking the Transnet Freight Rail export coal line with the existing Majuba Power Station rail yard. The inten- tion of the rail line is to transport 21 million ton per annum of coal in 100 jumbo wagon trains. The rail line forms part of the Majuba Power Station coal supply system. The earthworks construction consists of cut to fill, cut to spoil and layer works activ- ities totalling 8 000 000 m 3 of material and an excess of 35 000 000 m 3 /km of overhaul.

tendons assembly area. The positioning of the batch plant was restricted to setting up outside the 1:100 year flood line. The exceptional aspect of this incre- mental launch bridge is that the box section was cast in one pour, i.e. the floor, the walls and the deck in one pour in a seven day cycle. Central pre-stress (concentric cable) is required during the construction stage. Central pre-stressing means that the pre- stressing cables are arranged such that the resultant compressive stresses at all points in a given cross section are equal and it does not matter whether tensile stresses occur in upper or lower portions of the superstruc- ture during launching process.

Project information • Company entering: Aveng Grinaker-LTA • Project start date: August 2013 • Project end date: September 2015 • Client: Eskom and Transnet • Main contractor: Aveng Grinaker-LTA • Architect: Transnet Capital Projects • Principal agent: Eskom • Project manager: Eskom • Consulting engineer: Transnet Capital Projects • Subcontractor: Amsteel Systems