2018 - 2022 Financial Plan Online Interactive

SEWER

2017 ACCOMPLISHMENTS

INCLUSION

 Initiated development of a draft Municipal Type Service Agreement (MTSA) with Semiahmoo First Nation to provide sanitary sewer for their existing community.

BUILT ENVIRONMENT & NEIGHBOURHOODS

 Developed a conceptual sanitary sewer servicing plan for Grandview Heights Area #3 Neighbourhood Concept Plan area.

 Completed the development of servicing strategies for the Abbey Ridge Local Area Plan area and the City Centre Neighbourhood Concept Plan area; and

ECOSYSTEMS

 Completed construction of four projects to eliminate the likelihood of sanitary sewer overflows to local watercourses.

EDUCATION & CULTURE

 Supported Metro Vancouver with their Grease Reduction Campaign and their Unflushables Campaign in an effort to reduce the disposal of grease and wipes in the sanitary sewer system.

INFRASTRUCTURE

 Completed the vacuum sewer replacement program in Bridgeview by completing Phases 3 and 4 of the replacement program;  Initiated a sewer rehabilitation and renewal program study for the Robson Creek Catchment and Birdland Catchment in an effort to reduce the Inflow and Infiltration (I&I) rate and to replace sewer assets that are at the end of their service life; and

Trenchless Tunneling

 Completed the Fergus Sanitary Pump Station, Forcemain and Odour Control Facility to service the southern portion of Sunnyside Heights Neighbourhood Concept Plan area and the Highway 99 Corridor Local Area Plan area.