BA-20-002
Project #
Useful Life 15
Project Name Fire Station #1 - Parking Lot Concrete Paving
Category Fire
Priority 2 Important-Provide Efficienci
Accounting Code
Status Active
Fund Building Asset IS Fund
Description In 2017 the lower parking lot at Fire Station 1 was paved with concrete. This item is to pave the remainder of the parking lot at Fire Station 1 with concrete. Total Project Cost: $125,000
Justification The parking lot at Fire Station 1 has reached the end of its useful life and needs to be resurfaced.
Expenditures
Total
2020
2021
2022
2023
2024
125,000 125,000
125,000 125,000
Construction/Maintenance
Total
Funding Sources
Total
2020
2021
2022
2023
2024
125,000 125,000
125,000 125,000
Building Internal Service Fund
Total
Budget Impact/Other