2020-24 Capital Improvement Plan
Capital Improvement Plan City of Shakopee, Minnesota
thru 2020 2024
Contact Public Works Director Department Sanitary Sewer Fund
Type Maintenance
Sewer-20-003
Project #
Useful Life 30
Project Name Sewer Service Lateral Pipe Rehabilitation
Category Sanitary Sewer
Priority 1 Critical for Safety/Preservati
Accounting Code 5872/6872
Status Active
Fund Sanitary Sewer Fund
Description This project constructs a new cured-in-place liner inside sanitary sewer services located along sewer mains that have been lined. Total Project Cost: $650,000
Justification Sewer services in the project area vary in age, pipe material and condition. Most are approaching their life expectancy and pose a high risk of collapse or blockage. The sewer main in the project area was previously lined and the bituminous street is not in need of repair. This project continues with the rehabilitation of the City's infrastructure in the older sections of the Community.
Expenditures
2020
2021
2022
2023
2024
Total
550,000 100,000 650,000
550,000 100,000 650,000
Construction/Maintenance Engineering/Administration
Total
Funding Sources Sanitary Sewer Fund
Total
2020
2021
2022
2023
2024
650,000 650,000
650,000 650,000
Total
Budget Impact/Other Lining of sanitary sewer service pipes from the sewer main to behind the curb and gutter significantly lowers the potential for a collapse or blockage that would require costly open excavation and repair of the street.
204