2020-24 Capital Improvement Plan
Capital Improvement Plan City of Shakopee, Minnesota
thru 2020 2024
Contact Public Works Director Department Sanitary Sewer Fund
Type Improvement
Sewer-24-002
Project #
Useful Life 50
Project Name West End (High Bluff) Lift Station
Category Sanitary Sewer
Priority 2 Important-Provide Efficienci
Accounting Code
Status Active
Fund Sanitary Sewer Fund
Description The 2019 Sanitary Sewer Master Plan identifies a lift station and forcemain system to serve the West End Development within the high bluff area. Total Project Cost: $980,000
Justification West end development will require the expansion of the trunk sanitary sewer system.
Expenditures Planning/Design Improvements
Total
2020
2021
2022
2023
2024
40,000
40,000 820,000 120,000 980,000
820,000
120,000 120,000
Engineering/Administration
40,000
820,000
Total
Funding Sources Sanitary Sewer Fund
Total
2020
2021
2022
2023
2024
40,000 40,000
120,000 120,000
820,000 820,000
980,000 980,000
Total
Budget Impact/Other