2021-25 Capital Improvement Plan

2021 2025 thru

Capital Improvement Plan City of Shakopee, Minnesota

Project #

BA-22-006

Project Name Fire Station #1 Water Softener

Contact Assistant City Administrator Department Building Internal Service Fund

Type Buildings

Useful Life 15

Category Fire

Priority 2 Important-Provide Efficiencies

Accounting Code

Fund

Status Active

Description The water softener at Fire Station 1 has reached the end of it's useful life. Total Project Cost: $18,000

Justification Water softeners are required due to the hardness of water in Shakopee and increases the life of plumbing in the building.

Expenditures

Total

2021

2022

2023

2024

2025

Equip/Vehicles/Furnishings

18,000

18,000

18,000

18,000

Total

Funding Sources

Total

2021

2022

2023

2024

2025

Building Internal Service Fund

18,000

18,000

18,000

18,000

Total

Budget Impact/Other

157