2022-2026 Capital Improvement Plan (Final)
thru 2022 2026
Capital Improvement Plan City of Shakopee, Minnesota
Department Capital Improvements Fund
Contact Public Works Director
Type Improvement
Project #
CIF-23-003
Useful Life 15
Project Name Whispering Oaks Trail & Sidewalk Connections
Category Trails
Priority 3 Less Important/Future Consi
Accounting Code
Status Active
Fund Capital Improvement Fund
Description This project is proposed to construct a new segment of bituminous trail on the east side of CSAH 18 from Whispering Oaks Trail, southerly to the city limits with Prior Lake, connecting to their newly connected trail extension with the Haven Ridge development. It will also extend concrete sidewalk along Wildflower Way from Whispering Oaks Trail, southerly to the city limits with Prior Lake, connecting their newly connected sidewalk extension. Justification Prior Lake has started the construction of the Haven Ridge development. They have constructed sidewalk and trail up to the Shakopee city limits south of Whispering Oaks. This project will complete the missing segments of sidewalk and bituminous trail. Total Project Cost: $62,500
Expenditures
Total
2022
2023
2024
2025
2026
Construction/Maintenance
55,000
55,000
Engineering/Administration
7,500
7,500
62,500
62,500
Total
Funding Sources
Total
2022
2023
2024
2025
2026
Capital Improvement Fund
47,500
47,500
Cost Sharing, County
15,000
15,000
62,500
62,500
Total
Budget Impact/Other The City has asked the County to include the portion of bituminous trail along CH18 in the County TIP, and has requested County cost participation.