2023-2027 Capital Improvement Plan

2023 2027 thru

Capital Improvement Plan City of Shakopee, Minnesota

Project #

IT-23-007

Project Name Fiber Redundancy Improvements

Contact I.T. Director Department I.T. Internal Service Fund

Type Improvement

Useful Life 10

Category IT Infrastructure

Priority 2 Important-Provide Efficiencies

Accounting Code

Fund I.T. Internal Service Fund

Status Active

Description Datacenters Redundancy Infrastructure

Total Project Cost: $100,000

Justification Project to continue to address single points of failure between our two datacenters. Additional fiber runs and equipment are needed to make this possible.

Expenditures

Total

2023

2024

2025

2026

2027

Equip/Vehicles/Furnishings

50,000

50,000

100,000

50,000

50,000

100,000

Total

Funding Sources

Total

2023

2024

2025

2026

2027

I.T. Internal Service Fund

50,000

50,000

100,000

50,000

50,000

100,000

Total

Budget Impact/Other Additional infrastructure costs are factored into the IT Internal Fund budget process.