2023-2027 Capital Improvement Plan

City of Shakopee 15-YR Capital Improvement Plan (2023-2037) FINAL August 31, 2022

Project Number

(CIF) Capital

Special

MSA Fund

SPUC Sanitary Sewer Storm Drainage

Park

Park Asset

Building Internal Service Fund

Total Project

Project

Improvement Fund Assessments

(Watermain)

Fund

Fund

Development

Fund

Cost

NOTES

PW Surface Water - Tractor, 6430 177 Kage 3Pt PW Surface Water - steep slope mower AEBI PW Surface Water - Sweeper Freightliner

Storm-TBD Storm-TBD Storm-TBD PA-32-01 PA-32-02 PA-32-21 PA-32-31 PA-32-41 BA-32-003 BA-32-XXX BA-32-XXX

$118,000 $211,000 $429,000

$118,000 $211,000 $429,000 $93,000 $22,000 $110,000 $165,000 $55,000 $50,000 $20,000 $60,000

Annual Trail Reconstruction Annual Fence Replacement Annual Parking Lot Rehabilitation

$93,000 $22,000 $110,000 $165,000 $55,000

Annual Playground Equipment and ADA Improvements

Annual Playground Court Resurfacing

Misc Energy Efficiency, Ergonomic Maint Ice Arena-HVAC (1 and 2 of 8 units)

$50,000 $20,000 $60,000

CH AC mini-splits (3)

$9,293,000

2032 Subtotal

$4,019,000

$501,000

$2,325,000

$50,000

$650,000

$1,173,000

$0

$445,000

$130,000

2033

Annual Pavement Rehabilitation Annual Bituminous Mill and Overlay

CIF-33-011 CIF-33-012 CIF-33-013 CIF-33-001

$250,000 $350,000 $169,000 $5,602,000

$250,000 $380,000 $169,000 $6,830,000

$10,000

$10,000

$10,000

Annual Trail Rehabilitation (along roadways) 2033 Full Depth Pavement Reconstruction County Roadway ADA/Intersection Improvements

$1,123,000

$35,000

$30,000

$30,000

$10,000

CIF-TBD

$65,000

$65,000

Trunk Sewer Extensions

Sewer-33-005

$205,000

$205,000

Annual Erosion/Pond Cleaning/Outlet Imp Annual Drainage and Flood Prevention Imp

Storm-33-010 Storm-33-011 Storm-33-012 Storm-33-731 Storm-TBD

$174,000 $112,000 $84,000

$174,000 $112,000 $84,000

Annual Storm Sewer Equipment Replacement/Repair Public Works Surface Water: Skidsteer Loader PW Surface Water - Excavator Crawler CX80 180

$8,200

$8,200

$140,000

$140,000

Annual Trail Reconstruction Annual Fence Replacement Annual Parking Lot Rehabilitation

PA-33-01 PA-33-02 PA-33-21 PA-33-31 PA-33-41

$95,000 $22,000 $112,000 $169,000 $56,000

$95,000 $22,000 $112,000 $169,000 $56,000

Annual Playground Equipment and ADA Improvements

Annual Playground Court Resurfacing

Misc Energy Efficiency, Ergonomic Maint

BA-33-003

$50,000

$50,000

$8,921,200

2033 Subtotal

$6,436,000

$1,123,000

$35,000

$40,000

$245,000

$538,200

$0

$454,000

$50,000

2034

Annual Pavement Rehabilitation Annual Bituminous Mill and Overlay

CIF-34-011 CIF-34-012 CIF-34-013 CIF-34-001

$250,000 $890,000 $172,000 $2,569,000

$250,000 $940,000 $172,000 $6,230,000 $209,000 $410,000 $400,000 $252,000 $178,000 $114,000 $86,000

$20,000

$20,000

$10,000

Annual Trail Rehabilitation (along roadways) 2034 Full Depth Pavement Reconstruction

$1,316,000

$2,275,000

$30,000

$30,000

$10,000

Trunk Sewer Extensions

Sewer-34-005 Sewer-TBD Sewer-TBD Sewer-TBD Storm-34-010 Storm-34-011 Storm-34-012

$209,000 $410,000 $400,000 $252,000

CSAH 83/TH 169 Trunk Sewer Crossing Expansion

Cured In Place Sewer Pipe Lining PW Sanitary - Vacuum Inductor Trailer

Annual Erosion/Pond Cleaning/Outlet Imp Annual Drainage and Flood Prevention Imp

$178,000 $114,000 $86,000

Annual Storm Sewer Equipment Replacement/Repair

269

C:\Users\nreinhardt\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\JA1DE4JA\2023 -15yr CIP

Page 8 of 10