Capital Improvement Plan City of Shakopee, Minnesota
Department Park Development Fund
Contact Director of Planning & Develo
Type Improvement
Project #
PR-22-002
Useful Life 30
Project Name Southbridge Regional Trail Connection (Savannah)
Category Trails
Priority 2 Important-Provide Efficienci
Accounting Code
Status Active
Fund Park Development Fund
Description The Parks System Master Plan provides guidance to complete a missing gap in the regional trail network through the Southbridge neighborhood from TH 169 to Southbridge Parkway. The exact route needs to be identified and vetted with the community. Justification Trail connections provides off street transportation through Southbridge neighborhoods and enhances Savannah Oaks Park where a trail stub is currently constructed. This trail search corridor is part of the RBTN Tier 2 network. This missing segment will also be instrumental with the of a TH 169 trail bridge crossing. Total Project Cost: $190,000
Expenditures
Total
2023
2024
2025
2026
2027
Planning/Design
30,000
30,000
Improvements
160,000
160,000
30,000
160,000
190,000
Total
Funding Sources
Total
2023
2024
2025
2026
2027
Cost Sharing
30,000
160,000
190,000
30,000
160,000
190,000
Total
Budget Impact/Other Annual maintenance estimated at $2,500