2023-2027 Capital Improvement Plan
thru 2023 2027
Capital Improvement Plan City of Shakopee, Minnesota
Department Park Development Fund
Contact Director of Planning & Develo
Type Huber Park
Project #
PR-23-002
Useful Life 30
Project Name Cultural Corridor
Category Park Improvements
Priority 2 Important-Provide Efficienci
Accounting Code 5934/6934
Status Active
Fund Park Development Fund
Description The Parks System Master Plan provides guidance for the "remodeling" and development of Huber Park addressing riverfront, connection improvements, playground update, veterans memorial feature, another small shelter, etc. Integrate park and trail to include overlooks and trail segments, connecting to the river. The city has also completed a cultural corridor plan in cooperation with Scott County Historical Society, SMSC and Three Rivers Park District. Total Project Cost: $5,675,000
The Riverbank Stabilization project is essential in order to complete the Cultural Corridor.
Cost share funding and grant opportunities will be sought from the MnDNR, Army Corp of Engineers, Watershed, State Bonding, etc.
Justification Huber Park is proposed to become one of the signature parks in the Parks Master Plan. This includes a new playground, riverbank stabilization and creation of a natural flooding area that will protect the main elements of the park. Playground has its own CIP.
Expenditures
Total
2023
2024
2025
2026
2027
Improvements
1,000,000
2,000,000
2,500,000
5,500,000
Engineering/Administration
75,000
100,000
175,000
75,000
1,100,000
2,000,000
2,500,000
5,675,000
Total
Funding Sources
Total
2023
2024
2025
2026
2027
Cost Sharing
1,000,000
2,000,000
2,500,000
5,500,000
Park Development Fund
75,000
100,000
175,000
75,000
1,100,000
2,000,000
2,500,000
5,675,000
Total
Budget Impact/Other The project is contingent upon Federal and/or State grants and cost sharing.