2023-2027 Capital Improvement Plan
thru 2023 2027
Capital Improvement Plan City of Shakopee, Minnesota
Department Capital Improvements Fund
Contact Public Works Director
Type Improvement
Project #
CIF-25-001
Useful Life 25
Project Name 2025 Full-Depth Pavement Reconstruction
Category Street Reconstruction
Priority 1 Critical for Safety/Preservati
Accounting Code
Status Active
Fund Capital Improvement Fund
Description This project is for the full depth reconstruction of the bituminous roadway for 12the Avenue from east of County Road 83 to Valley Park Drive as shown on the map below. Converting this roadway from a 4-lane to a 3-lane (with a continuous two-way left turn lane will be evaluated as part of the project planning and design). Additionally, the intersection of 12th Avenue and Valley Park Drive will be evaluated for proper traffic control and configuration. Total Project Cost: $1,800,000
Utility, curb and gutter repairs and improvements will be evaluated and included with this project.
Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure. The City must reconstruct pedestrian ramp facilities to comply with its ADA Transition plan adopted in 2018, increasing the cost of these projects compared to previous years' projects.
Expenditures
Total
2023
2024
2025
2026
2027
Construction/Maintenance
1,650,000
1,650,000
Engineering/Administration
75,000
75,000
150,000
75,000
1,725,000
1,800,000
Total
Funding Sources
Total
2023
2024
2025
2026
2027
Capital Improvement Fund
75,000
1,205,000
1,280,000
Cost Sharing, SPUC
5,000
5,000
Sanitary Sewer Fund
5,000
5,000
Special Assessments
500,000
500,000
Storm Drainage Fund
10,000
10,000
75,000
1,725,000
1,800,000
Total
Budget Impact/Other Required ADA improvements are generally unfunded mandates to improve accessibility and to minimize liability.