2024-28 Capital Improvement Plan
thru 2024 2028
Capital Improvement Plan City of Shakopee, Minnesota
Department Park Asset Internal Serv. Fun
Contact Public Works Director
Type Neighborhood Park
Project #
PA-28-04
Useful Life 25
Project Name Pheasant Run Playground and Sign Replacement
Category Public Works
Project Code PA2804
Priority 3 Less Important/Future Cons
Accounting Code
Fund Park Asset IS Fund
Active
Status
Total Project Cost: $160,000
Description Originally built in 2003, complete replacement of the playground equipment, meet ADA requirements, surface material, drain tile, and border sections if needed. We will also be adding the approved park signage design to this project.
Justification Originally built in 2002, complete replacement of the playground equipment, meet ADA requirements/upgrades, surface material, drain tile, and border sections if needed. Update ID sign for the park
Expenditures
Total
2024
2025
2026
2027
2028
Equip/Vehicles/Furnishings
148,500
148,500
Engineering/Administration
11,500
11,500
160,000
160,000
Total
Funding Sources
Total
2024
2025
2026
2027
2028
Park Asset Internal Service Fund
160,000
160,000
160,000
160,000
Total
148