Schleper Stadium ADA Ramp Rehabilitation 2026 thru 2030 Project Details Shakopee, MN Project # Project Name

PA-26-04

Schleper Stadium ADA Ramp Rehabilitation

Total Project Cost

$70,000

Contact

Public Works Director

Department

Park Asset Internal Serv. Fund

Type

Improvement 1 - Have to do

Category

Park Improvements

Priority

Status

Active

Useful Life

30 years

Fund

Park Asset IS Fund

Description Replacing wood ramp with aluminum ADA ramping system.

Justification Ramp has reached its expected life, is deteriorating, and is in need of maintenance for safety.

Expenditures

2026 70,000 70,000 2026 70,000 70,000

2027

2028

2029

2030

Total 70,000 70,000 Total 70,000 70,000

Construction/Maintenance

0 0

0 0

0 0

0 0

Total

Funding Sources

2027

2028

2029

2030

Park Asset Internal Service Fund

0 0

0 0

0 0

0 0

Total