2026-2030 Capital Improvement Plan

Tahpah Park Lights (Field 2 & 3) 2026 thru 2030 Project Details Shakopee, MN Project # Project Name Total Project Cost Department Category

PA-29-04

Tahpah Park Lights (Field 2 & 3)

$505,000

Contact

Public Works Director

Park Asset Internal Serv. Fund

Type

Improvement 2 - Smart to do

Park Improvements

Priority

Status

Active

Useful Life

30 years

Fund

Park Asset IS Fund

Description Replace existing halogen lights, originally installed in the 1980's, with LED at fields two and tree at Tahpah Park.

Justification Lights are halogen and have reached their life expectancy. LED on timers will provide energy cost savings and improved field lighting quality. This is a dual-use field for softball in the summer and football in the fall.

Expenditures Improvements Planning/Design

2026

2027

2028

2029

2030

Total

437,000 68,000 505,000

0 0 0

0 0 0

0 0 0

437,000

0 0 0

68,000

Total

505,000

Funding Sources

2026

2027

2028

2029

2030

Total

505,000 505,000

Park Asset Internal Service Fund

0 0

0 0

0 0

505,000 505,000

0 0

Total

150