2026-2030 Capital Improvement Plan

Riverbank Stablization 2026 thru 2030 Project Details Shakopee, MN

Project #

PR-23-002

Project Name

Riverbank Stablization

Total Project Cost

$17,610,000

Contact

City Engineer Improvement 1 - Have to do

Department

Park Development Fund

Type

Category

Park Improvements

Priority

Status

Active

Useful Life

50 years

Accounting Code

5934/6934

Fund

Park Development Fund

Description Stabilize sections of the Minnesota River riverbank that has eroded along the city's parallel trunk sanitary sewer line that flows to L-16 and at storm sewer outlets. An evaluation was completed in 2023 to determine the scope and cost of this project. This project is essential in order to complete Huber Park and the Cultural Corridor project. Cost share funding and grant opportunities have been obtained from State Bonding and Federal Funds along with a grant from LCCMR and Watershed Based Implementation Funding. Additional funding opportunity will be applied for from various grants and sources.

Justification Huber Park is one of the signature parks in the Parks Master Plan. This includes the recently completed playground, riverbank stabilization, cultural corridor and creation of a natural flooding area that will protect the main elements of the park. Eroded riverbank needs to be stabilized to protect the city's adjacent trunk sanitary sewer, repair erosion along the riverbank and at outlets, and to minimize future erosion (Minnesota River is impaired). The stabilized river banks will help create areas for the planned Art Plaza and Veterans Memorial.

Prior

Expenditures

2026 2027 2028 2029 2030

Total

15,110,000

1,800,000

Improvements

15,110,000

0 0 0

0 0 0

0 0 0

0 0 0

700,000

Engineering/Administration

700,000

Total

15,810,000

15,810,000

Prior

Funding Sources State Bonding Funds

2026 2027 2028 2029 2030

Total

6,460,000 3,500,000 1,760,000 1,549,300 1,248,700 1,000,000

1,800,000

6,460,000 3,500,000 1,760,000 1,549,300 1,248,700 1,000,000

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

Cost Sharing, MnDOT/Federal

Sanitary Sewer Fund

Grants

Storm Drainage Fund

Park Development Fund

200,000 92,000

Park Asset Internal Service Fund

200,000

Cost Sharing

92,000

Total

15,810,000

15,810,000

Budget Impact The City received following dedicated funds for the project:

$8,260,000 from State Bonding $3,500,000 EPA Grant $149,297 WBIF for downtown stormwater treatment $1,400,000 LCCMR Funds The City share of the Riverbank Stabilization project would be funded primarily from the Sanitary Sewer, Park Dedication and Storm Drainage Funds.