2026-2030 Capital Improvement Plan
Safe Routes to School 2026 thru 2030 Project Details Shakopee, MN Project # Project Name
CIF-26-010
Safe Routes to School Infrastructure Improvements
Infrastructure Improvements Total Project Cost $400,000 Department
Contact
City Engineer Improvement 2 - Smart to do
Capital Improvements Fund
Type
Category
Engineering
Priority
Status
Active
Useful Life
30 years
Description The City was awarded $272,000 in Safe Routes to School Infrastructure Grant funds for improvements to Adams St, Fuller St and Quail Drive. The improvements are to support student safety for those walking, biking and rolling to school at Sweeney Elementary, Shakopee High School and Sun Path Elementary schools.
Justification The City's local share of the project costs include improvements at Sweeney Elementary School that are not eligible for grant reimbursement. Those costs include improvements at Lions Park and on the school property to relocate access to provide improved queuing off of Adams St. Those improvements would only be implemented if supported by the School District.
Expenditures
2026
2027
2028
2029
2030
Total
385,000 15,000 400,000
Construction/Maintenance Engineering/Administration
385,000
0 0 0
0 0 0
0 0 0
0 0 0
15,000
Total
400,000
Funding Sources
2026
2027
2028
2029
2030
Total
272,000 128,000 400,000
Grants
272,000 128,000 400,000
0 0 0
0 0 0
0 0 0
0 0 0
Capital Improvement Fund
Total
62
Produced Using Plan-It CIP Software